Comments
Please use this page to make a comment or suggestion about library services. We will post your suggestion as well as a response.
Comments from Previous Years
1 Hi. Can we please get Bascom to reopen the patio after 5PM and on weekends? This is where students go to microwave their food and eat, but when it is locked students can no longer use the microwaves or eat there. Could we either get this changed such that those with badges can enter the area, or can we get microwaves available for students at Calder? One of these seems reasonable
Another option is that the student lounge in Rosensteil is accessable nights and weekends and does still have a microwave that can be used.
Answered by Kimberly Loper, Executive Director of the Calder Memorial Library and Associate Dean for Health Information Services
2 Hi. Could we please get environmental services to do a deep cleaning of the building (and specifically the 3rd floor history of medicine room), followed by a cleaning by a insect terminator? There are an abundance of ants in the HoM room and it is quite gross. Ants continuously crawl over the tables and it needs to be fixed. Thanks
Answered by Kimberly Loper, Executive Director of the Calder Memorial Library and Associate Dean for Health Information Services
3 When will the second floor renovation be done?
Thank you for your question. The 1st phase (flooring) of the remodel project is partly done. Unfortunately the schedule was pushed back a few weeks because of hurricane Irma. Deselection of books and removal of shelving is complete. The bid/quote process for flooring installation was completed on November 30th. A P/O for flooring was submitted on December 1st. Once the carpet tile is removed, the floor will need to be sanded to remove old glue and then the floor will be leveled. Because the 2nd floor is open to the 1st floor, Administration is currently working with Facilities to obtain quotes for dust containment and we hope to have all quotes and to complete the flooring phase by the end of December 2017.
The 2nd phase (classroom buildout) has several more stages. The tentative project schedule for phase 2 is:
Documents/Engineering start 12/04/2018
Bidding start 1/15/2018
Permits start 2/05/2018
Construction start 3/19/2018
Completion end 6/18/2018
We realize construction can be difficult and disruptive. Thank you for your patience while we make these much-needed improvements to your library.
Answered by Kimberly Loper, Executive Director of the Calder Memorial Library and Associate Dean for Health Information Services
4 More outlets/ways to plug in a laptop charging cable in the 3rd floor study room!!! Please!!! Especially from the tables that located far from wall outlets, the cable splitters don't reach them.
Answered by Kimberly Loper, Executive Director of the Calder Memorial Library and Associate Dean for Health Information Services
5 I think the bathrooms should also be cleaned an additional time during the middle of the day. Although they are cleaned at night, by the mid-afternoon the bathrooms are destroyed.
Answered by Kimberly Loper, Executive Director of the Calder Memorial Library and Associate Dean for Health Information Services
6 Please turn the air conditioning down. The library is freezing.
If you could let us know specifically where it is freezing, we will work with Facilities to see if we can resolve the issue and at least increase the temperature to a relatively comfortable level.
Answered by Kimberly Loper, Executive Director of the Calder Memorial Library and Associate Dean for Health Information Services